-
-
Earthwork (Grading, Excavation and Filling, Foundations)
-
-
Asphaltic
Concrete
-
-
Reinforcing
Steel
-
-
Concrete
Batch Plant
-
-
Concrete
-
-
Shotcrete
-
-
Pre-Tensioned
Concrete
-
-
Post-Tensioned
Concrete
-
-
Masonry
-
-
Structural
Steel and
-
-
High
Strength Bolting
-
-
Nondestructive
Testing
-
-
Spray-Applied
Fireproofing
-
-
Glu
Lam and Truss Joists
-
-
Shear
Walls and Floor Systems Used as Shear Diaphragms
|
-
SECTION 10 - STRUCTURAL STEEL AND HIGH STRENGTH
BOLTING
OBJECTIVE
The customary practice of fabrication
of steel in the shop prior to erection conveniently allows division
of observation of structural steel into two basic categories,
shop and field. While the purpose is to assure that proper quality
control is exercised at each location, the environment differs.
Often the shop is fabricating other projects concurrently and
may operate two or three shifts per day. The shop work is closely
related to mass production, while the field work relates closer
to handcrafting.
These duties should be performed
by qualified special inspectors under the direct supervision
of the materials engineering laboratory. To better achieve the
objective of quality assurance, it is wise to use only one agency
to fulfill the duties of both shop and field observation.
OBSERVATION DUTIES
A. Documents
- Review the approved plans, specifications,
and approved shop drawings.
- Review applicable sections of
referenced codes, particularly the American Welding Society Structural
Welding Code (AWS D1.1) and the Manual and Specifications of
the American Institute of Steel Construction (AISC).
- Review welding procedure qualifications
when other than standard AWS prequalified joints and procedures
are involved.
B. Mill Test Reports
- Review mill test reports and
check heat numbers with material as received. Verify that proper
identification of steel is maintained during fabrication.
C. Sampling and Testing
- When required by project specifications
(particularly schools and hospitals), mark sample location with
steel stamp on each piece tested.
- Record sample number and location
and check that delivered to laboratory and tested.
- When steel members are delivered
to finish length and no "crop ends" are available for
sample cutting, coordinate cutting and patching requirements
with architect/engineer and fabricator.
D. Welding Observation
- Check each welders certification
and verify that the welder does work only as covered by his certification.
- Keep a written record of each
welder by name, his identifying steel mark, and the percentage
of rejectable welds.
- Upon detection of a rejectable
weld (either visually or by nondestructive test), the inspector-in-charge
will notify the welder and/or his foreman for verification of
defect. The inspector-in-charge will observe removal of defects
and repairs to check whether acceptable procedures were used.
- Check structural members for
thickness adjacent to welds.
- Inspect joints for proper preparation,
including bevel, root faces, root opening, etc.
- Check the type and size of electrodes
to be used for the various joints and positions. Check the storage
facilities to see if they are adequate to keep the electrodes
dry.
- Observe the technique of each
welder periodically with the use of a welding inspection shield.
- Verify the use of proper preheat
and interpass temperatures.
- Observe multi-pass welds continuously.
Continuous observation is defined as follows: The inspector is
present in the welding area at all times. The extent of inspection
of individual welds will depend on the number of operators welding.
- Observe single pass fillet welds
periodically (in accordance with code requirements), after determining
that the operator is capable of producing the welds required.
- If straightening or restraining
of weldments is necessary, verify that approved methods will
be used.
- Tag or stamp accepted weldments
with the inspectors identification stamp.
E. Workmanship
- Check straightening and bending
procedures.
- Check cut edges, including those
flame cut, sheared, or milled.
- Check bolt holes in major connection
for size.
F. Additional Field Duties
- Discuss welding sequence for
general construction plans and for specific joint sequence with
steel contractor and engineer to verify proper sequence to minimize
restraint.
- Curing adverse weather conditions,
check that adequate steps are taken to prevent moisture penetration
at welding location.
G. High Strength Bolting
- Sample high strength bolts,
washers, and nuts for testing from the lots in the shop or on
the jobsite, if required.
- Review type of joint specified
(i.e. slip critical, nonslip critical).
- Check bolts, nuts and washers
for compliance to project specifications.
- Review the procedure for installation
of bolts. The amount and type of inspection during installation
will depend on the method used.
- Check joint surfaces to verify
that they are free of burrs, dirt, etc.
- Verify installation procedures
meet minimum bolt tensions required by code.
- Check calibration of wrenches
for tightening capacity in a wrench calibrator.
H. Painting
- Verify cleaning operations to
all surfaces to condition specified.
- Verify conformance of paint
to specification.
- Verify application method, brush,
roller, or spray.
- Check for thickness of each
coating, final thickness, and holidays.
- Check touch-up for final finish.
I. Reports
- Submit written progress reports
describing their tests and observations made and showing the
action taken to correct nonconforming work. Itemize any changes
authorized by architect/engineer. Report all uncorrected deviations
from plans or specifications.
-
-
- home - who we are - guidelines for special inspection
- structural tests and inspection
schedule - meeting schedule
-
Please send your comments
and questions regarding this website to the webmaster.
|