-
-
Earthwork (Grading, Excavation and Filling, Foundations)
-
-
Asphaltic
Concrete
-
-
Reinforcing
Steel
-
-
Concrete
Batch Plant
-
-
Concrete
-
-
Shotcrete
-
-
Pre-Tensioned
Concrete
-
-
Post-Tensioned
Concrete
-
-
Masonry
-
-
Structural
Steel and
-
-
High
Strength Bolting
-
-
Nondestructive
Testing
-
-
Spray-Applied
Fireproofing
-
-
Glu
Lam and Truss Joists
-
-
Shear
Walls and Floor Systems Used as Shear Diaphragms
|
-
SECTION 2 - ASPHALTIC CONCRETE
OBJECTIVE
The performance of asphaltic
concrete pavement is as much affected by the careful construction
of the subgrade and base, as it is by the control of the asphaltic
concrete itself. Therefore, the paving inspector must be knowledgeable
in soils as well. The purpose of observation and testing of asphaltic
concrete paving is to verify that the paving contractor and his
supplier are exercising adequate quality control in their operations
and are providing a finished product that complies with the project
plans and specification requirements.
This objective can best be achieved
by qualified special inspectors performing the following duties
under the direct supervision of the materials engineering laboratory.
OBSERVATION DUTIES
A. Documents
- Review the approved plans and
specifications, and meet with contractor and suppliers before
construction to discuss project and to verify that requirements
for testing and observation are well understood.
- Review material certificates
and test reports for compliance with job specifications.
- Prepare or review mix designs
for compliance to project requirements.
B. Sampling of Materials
- Sample and perform preliminary
tests on proposed aggregates and asphalt cement (gradation, soundness,
abrasion, stripping, etc.)
C. Subgrade and Base
- Confirm that sources of materials
have been sampled and approved.
- Verify that materials delivered
are of uniform quality.
- Verify that control testing
of subgrade materials is being performed and recorded as required.
- Verify that subbase and bases
courses are of the source, type, thickness and density specified.
- Verify that soil sterilization
is provided, if required.
- Refer to Section 1, Earthwork
for additional details.
D. Batch Plant
- The special inspector should
become familiar with the appearance and physical characteristics
of the mix to be used by observing visually the finished mixture
so that unsatisfactory conditions may be readily recognized.
- Check the batch plant facilities
prior to production of asphaltic concrete mixture.
- Check aggregates in stockpile
to verify conformance to materials utilized in the design.
- Check the bin weights of the
aggregate fractions and asphaltic cement (batch plant only).
- Check the temperature of the
mixed batches on the truck.
- Perform hot-bin gradations of
the blended aggregates (where applicable).
- Verify cold-bin feeds and hot-bin
batch weights are adjusted as necessary to produce the job-mix
formula within tolerance.
- Before loading, truck beds should
be checked for cleanliness and absence of materials that might
be detrimental to the mix.
- Coordinate with the job site
inspector to obtain a uniform and consistent asphaltic concrete
mixture.
E. Spreading and Paving
- The field inspector should contact
the batch plant inspector promptly should conditions be observed
during placement and spreading operations that suggest a need
for change at the plant. The following items should be addressed
prior to and during placement operations:
- Area to be paved, cleaned
and properly primed, or tack coated.
- Leveling course installed where
required.
- Suitability of spreading and
paving equipment.
- Asphalt mix temperature when
delivered, and after final rolling, is within limits required.
- Density tests by nuclear gauge
during rolling.
- Thickness control by adequate
placement and compaction.
- Sampling of asphaltic concrete
at jobsite during placement for laboratory testing (extraction,
gradation, stability, etc.)
- Core samples taken for verification
of thickness and density of in-place asphaltic concrete.
- Application of seal coat and
curing in accordance with specification requirements, if required.
F. Verification Tests
- Stability and density, bulk
specific gravity, and maximum specific gravity.
- Asphalt content by extraction.
- Aggregate gradation of the mixture
from extracted sample.
- Physical properties of the asphalt
cement: Penetration, viscosity, ductility, and specific gravity.
- Aggregate quality: Los Angeles
abrasion, liquid limits of soils and plastic limit and plasticity
index, and sieve analysis.
- Field density.
- Thickness determination.
- Smoothness tolerance.
G. Reports
- Submit written progress reports
describing the tests made and showing the action taken to correct
nonconforming work. Itemize any changes authorized by architect
engineer. Report all uncorrected deviations from plans of specifications.
-
-
- home - who we are - guidelines for special inspection
- structural tests and inspection
schedule - meeting schedule
-
Please send your comments
and questions regarding this website to the webmaster.
|