-
-
Earthwork (Grading, Excavation and Filling, Foundations)
-
-
Asphaltic
Concrete
-
-
Reinforcing
Steel
-
-
Concrete
Batch Plant
-
-
Concrete
-
-
Shotcrete
-
-
Pre-Tensioned
Concrete
-
-
Post-Tensioned
Concrete
-
-
Masonry
-
-
Structural
Steel and
-
-
High
Strength Bolting
-
-
Nondestructive
Testing
-
-
Spray-Applied
Fireproofing
-
-
Glu
Lam and Truss Joists
-
-
Shear
Walls and Floor Systems Used as Shear Diaphragms
|
-
SECTION 3 - REINFORCING
STEEL
OBJECTIVE
The purpose of reinforcing steel
observation is to give assurance that the supplier is exercising
satisfactory control over production, fabrication and placing
of reinforcing steel so that it meets the project specifications
and applicable codes and industry standards.
This objective can best be achieved
by qualified special inspectors who diligently perform the duties
listed below while under the direct supervision of the materials
engineering laboratory.
OBSERVATION DUTIES
A. Documents
- Review the approved plans, specifications,
and approved shop drawings.
- Review applicable sections of
referenced codes, such as: the Uniform Building Code and Uniform
Building Standards (ICBO); the Building Code, Requirements for
Reinforced Concrete (ACI-318) by the American Concrete Institute
(ACI); the Manual of Standard Practice of the Concrete Reinforcing
Steel Institute (CRSI); the Reinforcing Steel Welding Code (AWS
D1.4) by the American Welding Society (AWS).
B. Mill Test Reports
- Verify reinforcing steel mill
test reports (when available) for mill markings and test data,
checking against project requirements.
- Sample material for tests directly
from unopened bundles when required by specifications.
C. Fabrication
- Check each shipment of reinforcing
steel for the following:
- Bar sizes and grades
are as specified.
- Mill marking is in conformance
with mill test reports.
- Check for corrosion, contaminants,
surface cracks and bars damaged in shipment.
- Check shop bends for specified
radius and cracks.
D. Placement
- During placement of reinforcing,
check for proper bar locations, alignment, laps, ties, form and
ground clearance, supports, field bend radii and cracks, gouges
or tack welds causing stress concentrations, removal of contaminants,
and hardened concrete.
- If welding of reinforcing is
required, it should be observed as defined in UBC Section 1701.5
(5.3), with particular emphasis on joint configuration, suitability
of low hydrogen electrodes, preheat and interpass temperatures,
and interpass slag removal. Check for welding procedures for
conformance to AWS D1.4.
- Prior to concrete placement,
check for complete installation and notify contractor of any
variations from plans and specifications. If variations are not
corrected prior to start of concreting, immediately notify the
design team representative for appropriate action.
- During concrete placement, check
that reinforcing stays in place and is adequately supported.
Check for removal of dirt, concrete spatter and grease.
- Check embedded items, including
anchorages, inserts, and bolts installed in concrete for compliance
to project documents. Verify they are solidly cast in place during
placement of concrete.
E. Reports
- Submit written progress reports
describing the tests and observations made and showing the action
taken to correct nonconforming work. Itemize any changes authorized
by architect/engineer. Report all uncorrected deviations from
plans or specifications.
-
-
- home - who we are - guidelines for special inspection
- structural tests and inspection
schedule - meeting schedule
-
Please send your comments
and questions regarding this website to the webmaster.
|