-
-
Earthwork (Grading, Excavation and Filling, Foundations)
-
-
Asphaltic
Concrete
-
-
Reinforcing
Steel
-
-
Concrete
Batch Plant
-
-
Concrete
-
-
Shotcrete
-
-
Pre-Tensioned
Concrete
-
-
Post-Tensioned
Concrete
-
-
Masonry
-
-
Structural
Steel and
-
-
High
Strength Bolting
-
-
Nondestructive
Testing
-
-
Spray-Applied
Fireproofing
-
-
Glu
Lam and Truss Joists
-
-
Shear
Walls and Floor Systems Used as Shear Diaphragms
|
-
SECTION 7 - PRE-TENSIONED CONCRETE
OBJECTIVE
Because the strength of materials
used in prestressed construction is significantly higher than
normal concrete construction, there has developed a strong quality
control program by plant manufacturers. As a result, the purpose
of pre-tensioned concrete plant observation is to verify the
actual control program and check its effectiveness.
This objective can best be achieved
by qualified special concrete inspectors performing the following
duties under the direct supervision of the materials engineering
laboratory.
OBSERVATION DUTIES
A. Documents
- Review the approved plans, specifications,
and approved shop detail drawings.
- Verify that concrete mix designs,
tensioning data, and calculations for stressing have been approved
by the reviewing authority.
- Verify that jacking equipment
has been calibrated.
B. Mill and Plant Test Reports
- Check conformance of all materials
to project specifications. Verify steel mill test reports for
prestressing steel and deformed bar steel. Verify mill markings
and tags. Verify cement mill test reports and certification.
- Check fabricators testing
facility and reporting of tests performed under fabricators
quality control program.
C. Sampling
- Sample and deliver or ship to
the laboratory for testing the following when independent tests
are required by project specifications:
- Concrete aggregates
- Prestressing strand or wire
- Reinforcing steel
- Steel used for structural steel
embedded items
D. Steel Fabrication of Embedded
Items
- Verify that qualified welders
are employed to perform welding of structural steel using welding
procedures qualified in accordance with AWS Structural Welding
Code.
E. Pre-Placement Observations
- Bed layout and form cleanliness.
- Quantity and spacing of reinforcing
and stressing steel.
- Location of inserts and embedded
items.
- Profile of stressing steel.
- Witness tensioning of prestressing
elements, measure elongation of strand, and record gauge pressure.
F. Tests and Observation During
Casting
- Perform batch plant observations.
- Conduct slump, air, and unit
weight tests. Request adjustments as necessary.
- Cast compression test specimens.
- Observe placement and vibration
of concrete in forms.
- Observe finishing treatment.
G. Post-Placement Tests and
Observations
- Observe curing procedures, temperatures,
and curing cycles.
- Monitor compressive strength
results for specified release strength.
- Witness stress transfer.
- Identify member by component
and date cast.
H. Field Erection
- Check members for damage during
storage or shipment.
- Check field installation and
structural connections.
I. Reports
- Submit written progress reports
describing the tests and observations made and showing the action
taken to correct nonconforming work. Itemize any changes authorized
by architect/engineer. Report all uncorrected deviations from
plans of specifications.
-
-
-
- home - who we are - guidelines for special inspection
- structural tests and inspection
schedule - meeting schedule
-
Please send your comments
and questions regarding this website to the webmaster.
|