Earthwork (Grading, Excavation and Filling, Foundations)
 
Asphaltic Concrete
 
Reinforcing Steel
 
Concrete Batch Plant
 
Concrete
 
Shotcrete
 
Pre-Tensioned Concrete
 
Post-Tensioned Concrete
 
Masonry
 
Structural Steel and
 
High Strength Bolting
 
Nondestructive Testing
 
Spray-Applied Fireproofing
 
Glu Lam and Truss Joists
 
Shear Walls and Floor Systems Used as Shear Diaphragms

 

SECTION 8 - POST-TENSIONED CONCRETE

OBJECTIVE

Post-tensioned concrete is normally constructed onsite rather than fabricated in plants. As a result, more responsibility is placed on the independent inspection agency to verify that quality control meets acceptable standards.

This objective can best be achieved by qualified special inspectors performing the following duties under the direct supervision of the materials engineering laboratory.

OBSERVATION DUTIES

A. Documents
  1. Review the approved plans, specifications and approved placing and stressing drawings furnished by the post-tensioning contractor.
  2. Review the reinforcing steel placing drawings to check whether they have been coordinated with the stressing drawing.
B. Mill Test Reports
  1. Check that reinforcing steel and post-tensioning steel supplied to job is properly identified and mill test reports show conformance to project specifications.
C. Sampling of Materials
  1. Sample and deliver to the laboratory for testing the following materials when required by project specifications:
    1. Concrete aggregates and cement
    2. Prestressing strand, rods or wire
    3. Reinforcing steel
    4. Steel used for structural inserts
D. Steel Fabrication of Embedded Items
  1. Visit fabrication plant.
  2. Verify that qualified welders only are welding in accordance with AWS Structural Welding Code.
  3. Verify that only qualified welding procedures are being used.
  4. Observe the welding operations and the finished product for defects and verify that corrections are made, if necessary.
E. Pre-Placement Observations
  1. Check the general layout, size, spacing, and profile of all reinforcing steel and post-tensioning steel.
  2. Observe all anchorages, inserts, embedded items, blockouts, conduits, etc.
  3. Calibrate or review current calibration data on the proposed stressing equipment.
F. Observation During Placement of Concrete
  1. Observe batch plant operations when required.
  2. Observe concrete placement and report any damage or misalignment of any embedded components (with particular emphasis at end anchorages).
  3. Cast compression test specimens.
  4. Test slump, air content, and unit weight. Request adjustment as necessary.
G. Stressing
  1. Verify that the concrete compressive strength meets the minimum required strength prior to post-tensioning.
  2. Check the stressing sequence and verify the required post-tensioning forces.
  3. Call to the attention of the structural engineer any out of tolerance discrepancy in force-elongation relationship, spelled concrete, broken tendons, or anchorage slippage.
  4. Verify friction losses where applicable.
  5. When using bonded tendons, observe grouting procedure.
H. Reports
Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work. Itemize any changes authorized by architect/engineer. Report all uncorrected deviations from plans or specifications.
 
 

home - who we are - guidelines for special inspection - structural tests and inspection schedule - meeting schedule
Please send your comments and questions regarding this website to the webmaster.