-
-
Earthwork (Grading, Excavation and Filling, Foundations)
-
-
Asphaltic
Concrete
-
-
Reinforcing
Steel
-
-
Concrete
Batch Plant
-
-
Concrete
-
-
Shotcrete
-
-
Pre-Tensioned
Concrete
-
-
Post-Tensioned
Concrete
-
-
Masonry
-
-
Structural
Steel and
-
-
High
Strength Bolting
-
-
Nondestructive
Testing
-
-
Spray-Applied
Fireproofing
-
-
Glu
Lam and Truss Joists
-
-
Shear
Walls and Floor Systems Used as Shear Diaphragms
|
-
SECTION 9 - MASONRY
OBJECTIVE
The purpose of special observation
for masonry is to verify that the workmanship and materials meet
the minimum standards required by code, as well as the project
specifications. This is particularly difficult in masonry work
where so much is dependent upon the capabilities of the individual
mason, as well as practices that have developed over the years
and have become the custom of the trade for the particular locality.
This requires experience and judgment by the inspector as well.
This objective can best be achieved
by qualified special inspectors performing the following duties
under the direct supervision of the materials engineering laboratory.
OBSERVATION DUTIES
A. Documents
- Review the approved plans and
specifications with the masonry contractor and architects
representative in a preconstruction meeting to verify level of
inspection required for the particular job. This is the time
to resolve any differences in local custom or practice of the
mason and requirements of the code and project specifications.
B. Mill Test Reports
- Verify that mill test certificates
for unit masonry, cement and reinforcing steel have been furnished
by supplier and are acceptable to the architect/engineer.
C. Sampling of Materials
- Sample and verify that the following
materials are delivered to laboratory for testing when required
by project specifications:
- Concrete block or brick
- Aggregates and cement for mortar
and grout
- Reinforcing steel as delivered
D. Storage of Materials
- Check that cement, lime, block
and brick are supported on pallets and covered to protect from
exposure to excessive moisture or drying.
- Check that aggregates for mortar
and grout are stored free from contamination and in such a manner
as to minimize segregation.
E. Preparation for Lay-Up
- Verify size and spacing of reinforcing
dowels.
- Verify that foundation concrete
is clean and prepared as required by specifications.
F. Lay-Up or Placing of Masonry
Units
- Verify whether high lift or
low lift procedures have been approved for use.
- Verify that cleanouts are provided
for first course of each pour, if high lift method is used.
- Check plumb and lay-up configuration.
- Check moisture condition of
masonry units.
- Verify that proper mortar ingredients
and batching techniques are being used and prepare mortar compression
test specimens.
- Check mortar time on board.
- Verify that head joints are
the same thickness as face shells or that full head joints are
used when specified.
- Check that mortar extrusions
(fins) are cleaned off inside.
- Check whether joints are tooled
as specified.
- Check required frequency of
masonry wall prisms and observe construction of same.
- Check for ties when specified.
- Check horizontal reinforcing
steel placing:
- Placed at correct course, laps
as specified.
- Check whether laps are staggered
in bond beams and corners as required.
- Check lintel bars over openings.
- Check hooks, if called for in
jambs.
- Check ties in piers, diameter,
spacing, and properly fastened.
- Check vertical reinforcing steel:
- Check bars at jambs,
corners and piers, and typical wall steel.
- Check whether tied a top and
bottom, and as required by project specifications.
G. Grouting Observations
- Verify that cells and starting
beds are clean. Check condition with light or mirror.
- Check whether dowels, anchor
bolts and inserts are all in place particularly at roof lines,
floor lines and intersecting wall lines.
- Check installation of cleanout
closures.
- Check grout mix and admixture
required, etc.
- Check slump in accordance with
the specifications.
- If low lift grouting, verify
that maximum masonry height is in accordance with the code before
grouting.
- Check that grout is stopped
below top for keying where required.
- Verify mechanical vibrating
during placement, and later during reconsolidation.
- Continuous observation is required
during grouting operations.
- Prepare grout specimens in absorbent
form, or as specified, for laboratory testing.
- Check that curing requirements
are being followed.
H. Reports
- Submit written progress reports
describing the tests and observations made and showing the action
taken to correct nonconforming work. Itemize any changes authorized
by architect/engineer. Report all uncorrected deviations from
plans or specifications.
-
- home - who we are - guidelines for special inspection
- structural tests and inspection
schedule - meeting schedule
-
Please send your comments
and questions regarding this website to the webmaster.
|